Morgan House
Grau General Contracting, LLC
 
Hauessler Progress as of 8/18/09

We have completed the exterior log staining and have applied the chinking between the
logs.  We are finishing up installation of the exterior handrails and roof gutters, and are in
the process of installing the interior doors and trim, drywall and wood paneling.  The
cabinetry is being fabricated and soon we will install the oak hardwood flooring.

(Click on images to enlarge)